Developing a power project
Coordinate land rights, permits and construction from the choice of site through commissioning.
Related guide Securing funding through project agreements · Grid connection agreement for a generator
Developing a renewable power plant or storage facility in Germany involves more than choosing a technology. The developer must plan the facility, obtain permits, arrange finance, oversee construction and prepare for operation. Each step depends on whether the project uses wind, solar energy, hydropower, biogas, batteries or pumped storage.
1. From site selection to operation
1.1 Five stages of project development
- Project initiation and site selection:
- Identify suitable land and routes for cables. Check grid access, nature conservation and heritage restrictions before securing the site.
- Applicable law
- The Federal Building Code (BauGB) governs municipal land-use planning and the planning conditions for development.
- Nature conservation law requires consideration of protected habitats, Natura 2000 sites and bird protection.
- Permitting:
- Determine which permits are needed and whether the project requires an environmental impact assessment or a preliminary screening. Use that finding to define the application documents.
- Applicable law
- For wind turbines and biogas installations, check the type of installation and applicable thresholds under German emissions control law (BImSchG and the Fourth Implementing Ordinance).
- Sections 6 and 7 and Annex 1 to the Environmental Impact Assessment Act (UVPG) distinguish projects subject to mandatory assessment from those subject to screening.
- Finance and competitive bidding:
- Check whether a bid is needed, for example in an auction under the Renewable Energy Sources Act (EEG).
- Model the combination of support payments, equity and debt needed to finance the project.
- Construction:
- Award the works contracts and monitor progress on site.
- Applicable law
- Public contracting authorities must assess the applicable procurement rules.
- Plan for occupational health and safety, including duties under the German Occupational Safety and Health Act.
- Commissioning and operation:
- Arrange the grid connection and integration into the power system.
- Assign responsibility for operation and maintenance before handover.
2. Wind power
2.1 Site and technology
- Onshore wind:
- Check the planning designation and the distances from residential areas that apply to the site.
- Consider conservation concerns and public participation early in the process.
- Offshore wind:
- Establish whether the wind farm lies in the exclusive economic zone or territorial waters.
- Marine environmental protection adds requirements for permitting and construction.
2.2 Legal framework
- Renewable Energy Sources Act (EEG):
- Check the EEG auction requirements for onshore wind, starting with section 22.
- The market premium can support direct sales of electricity where the statutory conditions are met.
- Wind Energy Area Requirements Act (WindBG):
- The Länder must make land available for onshore wind in accordance with the statutory area targets.
- Offshore Wind Energy Act (WindSeeG):
- This act governs offshore planning and auctions.
2.3 Project risks
- Allow for permitting procedures that can take several years.
- Disputes may arise with residents and conservation organisations.
- Grid congestion can delay connection and affect the energy delivered.
3. Solar photovoltaics
3.1 Site and technology
- Ground-mounted solar:
- Check whether the intended agricultural land qualifies, including any designation as a less-favoured area.
- Assess soil sealing and landscape protection requirements.
- Rooftop systems:
- Check the building rules of the relevant Land. Small rooftop installations may benefit from procedural exemptions.
- Model electricity used on site separately from power sold to the grid. The former EEG levy provision in section 61 has been repealed.
3.2 Legal framework
- Renewable Energy Sources Act (EEG):
- Larger installations may need to participate in a solar auction to qualify for support.
- Smaller systems can qualify for a feed-in tariff if the statutory conditions are met.
- Federal Building Code (BauGB):
- Check planning permission for the proposed ground-mounted installation at the chosen site.
3.3 Project risks
- Agricultural operators and solar developers may compete for the same land.
- Connection works can be substantial, especially for a large solar farm.
- Test the financial model against lower support rates.
4. Hydropower
4.1 Site and technology
- Small hydropower:
- Existing mills and weirs may provide infrastructure for a project.
- Large hydropower:
- Assess the potential contribution to baseload generation over the long planning horizon.
4.2 Legal framework
- Federal Water Act (WHG):
- Check ecological requirements and the minimum flow that must remain in the watercourse.
- Renewable Energy Sources Act (EEG):
- Section 40 EEG sets the reference value for eligible hydropower and contains conditions for existing plants and upgrades.
4.3 Project risks
- Plan for fish protection and continuity of the watercourse.
- Works altering river channels may conflict with conservation objectives.
5. Biogas
5.1 Feedstocks and heat use
- Agricultural use:
- Anaerobic digestion converts slurry, maize or suitable waste into biogas for energy production.
- Combined heat and power:
- A combined heat and power unit can supply both electricity and usable heat.
5.2 Legal framework
- Renewable Energy Sources Act (EEG):
- Check whether the biomass auction rules apply to the proposed installation.
- For eligible biogas installations, section 50a EEG provides for a supplement for flexible installed capacity.
- Federal Immission Control Act (BImSchG):
- Determine the permitting requirements by plant type and size. Address emissions and odour in the application.
5.3 Project risks
- Energy crops compete with other uses of agricultural land.
- Rising feedstock prices can reduce operating margins.
6. Electricity storage
6.1 Battery storage projects
- Legal framework:
- Section 17 EnWG covers grid connection. Section 118(6) EnWG contains transitional rules for exemptions from certain network charges, subject to specific conditions.
- Assess EEG eligibility for the electricity discharged and the availability of a suitable KfW financing programme separately.
- Project risks:
- Allow for capital costs, loss of usable capacity and the expected battery replacement date.
- Fire protection and other safety requirements can lengthen the approval process.
6.2 Pumped storage
- Legal framework:
- Identify the water permits needed for the reservoirs and their operation.
- For electricity fed into the grid after storage, examine section 19(3) and the following subsections of the EEG. Entitlement depends, among other things, on the source and allocation of the electricity.
- Project risks:
- Construction is expensive and planning lead times are long.
- Landscape changes and conflicts with conservation interests may limit the project.
7. Risks across the project
7.1 Permitting
- Budget time for environmental studies and administrative review.
- Identify concerns raised by conservation bodies and local residents’ groups.
7.2 Financing
- Distinguish projected EEG revenues from financing under KfW programmes.
- Check whether the project remains viable if support rates fall.
7.3 Grid connection
- Identify bottlenecks that could delay integration of a large project.
- Agree who will undertake the connection works and who bears the cost.
8. Developments to consider
8.1 Digital systems
- Networked metering and control systems can improve project planning and daily operation.
- Digital platforms can simplify the submission and processing of permit applications.
8.2 Hybrid power plants
- A hybrid project can combine wind, solar PV and storage at one site. Check its metering and support arrangements at the design stage.
8.3 European coordination
- Follow EU measures to align and streamline national permitting procedures.
- Cross-border projects, including offshore wind farms, need coordination between the authorities and grid operators involved.
Four practical examples
A developer needs an additional cooling-water pipeline. We coordinate rights along the route with the permit application so that the approved alignment can actually be built.
A turbine supplier offers indicative delivery dates. We identify the construction stages that depend on delivery and agree binding milestones and remedies for delay.
An operator plans to change fuel. We check whether the permit must be amended and which specifications or volumes in the supply contracts need to change.
A buyer takes over a former plant site. We distinguish dismantling costs from contaminated-soil risks and allocate responsibility for each in the purchase agreement.
§ 7 UVPG · § 3 WindBG · § 35 WHG · § 19 EEG · § 40 EEG · § 50a EEG · § 17 EnWG · § 118 EnWG