An engineering, procurement and construction agreement assigns design, purchasing and construction to a contractor. For a wind farm, solar park, biogas plant or storage power station, specify who delivers each interface and which tests demonstrate an operational plant at handover.
1. Parties and purpose of the example
XYZ Renewables GmbH, Musterstraße 1, 12345 Musterstadt, represented by managing director Max Mustermann, commissions ABC EPC Solutions AG, Energieallee 10, 54321 Energiehausen, represented by board chair Lisa Beispiel. The fictional contractor undertakes to design, procure and build a turnkey generating plant meeting the agreed specifications and applicable law.
2. Scope and owner’s contributions
The contractor designs the plant, buys all components and materials, manages construction and commissions the installation. The owner supplies the necessary permits and site access and pays the agreed price. An extended scope adds operation and maintenance for the first two years after commissioning. Under a narrower scope the owner supplies named items or services, such as earthworks.
3. Term and milestones
The illustrative contract starts on 1 January 2025 and runs to acceptance, subject to obligations that survive. Design is due on 30 March, procurement on 30 June, construction on 30 September and commissioning on 31 October 2025. One option allows postponement by up to 30 days by written agreement. Another proposes a delay penalty of 0.1% of contract value per calendar day. Negotiate the trigger, calculation base and aggregate cap and check whether the clause is enforceable.
4. Price and payment
The €10 million lump sum covers materials, labour and incidental costs. The example pays 30% at signature, 40% on completion of procurement and 30% after successful commissioning. Alternatives allow monthly progress payments or a bonus if measured output exceeds the agreed target.
5. Technical requirements
Prepare design and permit documents to the applicable DIN and VDE standards. Build to the network operator’s connection requirements and applicable German renewable energy legislation (EEG). Commission after successful functional testing. The contractor could guarantee at least 95% of rated output. A further option permits the owner to request specification changes during construction if completion is unaffected. Record the cost effects as well.
6. Acceptance, defects and guarantees
The example schedules technical inspection within 30 days of commissioning. Record performance, defects, reservations and the owner’s acceptance decision. For deemed acceptance under section 640(2) BGB, check completion, an appropriate deadline and the owner’s response. A technical test alone does not establish that those conditions are met.
An illustrative 24-month contractual guarantee runs from acceptance, with a possible ten-year module guarantee. Statutory defect claims and limitation periods require separate assessment under section 634a BGB. Alternatives provide a five-year guarantee for the whole plant or free operating and maintenance personnel for two years after acceptance.
7. Liability and interruptions
The example proposes a contractor cap of 10% of contract value for direct loss and exclusions for indirect loss and lost profit. Check mandatory exceptions and standard terms control. Intentional liability cannot be waived in advance under section 276(3) BGB. The owner bears agreed consequences of delay or extra costs caused by missing permits or inadequate site access. Options expressly preserve unlimited liability for gross negligence and intent or define relief for unavoidable events such as natural disasters.
8. Disputes and alternative delivery models
The example starts with mediation, followed by arbitration under the German Arbitration Institute (DIS) rules. Alternatives are ICC arbitration seated in Zurich or ordinary courts, for example at the owner’s seat where a jurisdiction agreement is valid. Define one route for deciding the merits.
Split EPC gives the owner separate design, purchasing and construction contracts and more choice of providers, with more coordination. Under EPCM a manager coordinates the work performed by specialist contractors. This may reduce costs but leaves interface and liability risks with the owner. A turnkey contract instead assigns delivery of an operational plant to one contractor, who prices the risks it takes. Match the model to the technical scope, budget and project risks.
Four practical examples
A transformer arrives late. Review the delay notice, substitute procurement and schedule impact. A plant misses its efficiency target at acceptance. Compare the test conditions with the guarantee.
The owner and general contractor dispute the earthworks. Allocate the work using the interface schedule. A contractor claims extra payment. Compare the instruction, quotation and site record.
§ 640 BGB · § 634a BGB · § 341 BGB · § 276 BGB · § 307 BGB