Financing an energy installation means aligning the loan agreement, project contracts and security with the same requirements for construction, drawdown and operation.
Security may be of little use if the land agreement ends immediately on termination or a replacement operator cannot continue without consent. Equally, the project company must be able to satisfy the conditions for first drawdown using documents it can actually obtain.
Direct agreements and drawdown
We compare the financing conditions with the land, construction, grid connection, maintenance and power marketing agreements. Direct agreements specify notification duties, periods to cure breaches and step-in by a qualified replacement operator. Before drawdown, the project company receives a list of outstanding consents and documents.
Four practical examples
A bank requires assignment of PPA revenues. The buyer will consent only against security of its own. We reconcile both agreements.
An EPC contractor can terminate for late payment. We negotiate notice to the lender and a cure period.
A landowner wants to check creditworthiness before consenting to a change of operator. We define criteria that can be tested in advance.
The battery supplier requires an advance before first drawdown. We examine bridge finance and an advance payment guarantee.