Negotiating electricity and gas supply agreements
Start with the plant’s production profile. When does it draw power, how much may volumes vary, and when could the supplier call for security? Compare each offer against the same demand profile. A long-term renewable power purchase agreement raises additional questions about generation shortfalls and guarantees of origin.
Energy contracts link suppliers, network operators, plant owners, developers and customers. Technical commitments, prices and legal responsibilities must fit together across German, European and, for cross-border projects, international rules.
Network connection, use and transfer
A connection agreement defines the interface between a plant or load and the electricity or gas network. Record the connection point, voltage, frequency, capacity, cost allocation and incident responsibilities. Section 17 EnWG governs general connection conditions. Offshore wind connections have specific rules under section 17d EnWG.
A network use agreement governs transport over the network. Check non-discriminatory access under section 20 EnWG and the basis for charges under section 21. A network transfer agreement addresses a different transaction, for example a municipal takeover or a change of concession holder.
Generation, offtake and plant operation
Under a power purchase agreement (PPA), a generator sells power to a customer or trader over an agreed period. A wind farm and an industrial buyer may agree a fixed price, delivery schedule and treatment of renewable attributes. For renewables feeding into the grid, an agreement can organise settlement. Under section 7 EEG, network operators may not make fulfilment of their statutory EEG duties conditional on signing a contract. Construction and operation require different terms, including engineering, procurement and construction (EPC) and operation and maintenance (O&M) agreements.
End-user supply, services, concessions and funding
Electricity and gas supply agreements range from variable and dynamic tariffs to individually negotiated industrial contracts. The basic supply duty under section 36 EnWG applies to the designated local supplier for eligible household customers on low-voltage or low-pressure networks. Energy service agreements may cover an audit, efficiency measures or a contractor operating equipment. A municipal concession covers rights to use public ways under section 46 EnWG. For project support, distinguish statutory entitlements, grant decisions and financing agreements, including EEG, KWKG and KfW programmes as applicable.
What decisions and statutes mean for a contract file
In Stromnetz Berkenthin (KZR 66/12), the German Federal Court of Justice addressed non-discriminatory municipal selection of a network concessionaire. Keep the published criteria with the bid assessment. For delayed offshore connections, check the binding completion date, outage periods and statutory compensation conditions under section 17e EnWG.
In Schulz and Egbringhoff (C-359/11 and C-400/11), the Court of Justice addressed advance information about the grounds, conditions and extent of price changes in basic supply. In PreussenElektra (C-379/98), the statutory minimum-price purchasing obligation on private suppliers in the scheme at issue did not itself involve a transfer of State resources. Each funding scheme requires examination of its financing mechanism.
European and international projects
The Electricity Directive (EU) 2019/944 and Gas and Hydrogen Directive (EU) 2024/1788 frame access, unbundling and consumer protection. Directive (EU) 2018/2001, as amended, addresses renewable energy. For a long-term PPA, review applicable market transparency and competition rules and the terms at the particular grid connection point.
Cross-border PPAs, including offshore projects, require coordination of delivery points, national rules, currency and price risk. Power plant contracts may provide for ICC or LCIA arbitration. Climate policy under the Paris Agreement provides context for contract negotiations: specify which party bears carbon costs and what evidence it must produce.
Drafting, disputes and data
Allocate delays, congestion and technical defects to the relevant contracts. Provide for changes to the regulatory and funding framework, routes to mediation or arbitration, and GDPR responsibilities where smart meters or energy management systems process personal data. Coordinated provisions make technical and commercial risks easier to trace across the project.
Four practical examples
A glass manufacturer needs volume flexibility for seasonal orders. We negotiate tolerances and the price for excess consumption.
A supplier asks for additional collateral. We check the trigger, cap and release conditions against the draft agreement.
A price adjustment clause refers to a discontinued index. We draft a replacement mechanism that both parties can verify.
A factory closes before the supply contract ends. We negotiate a transfer of the remaining volume to another group site.