A wind farm, solar park or storage project depends on several contracts performing to the same timetable. Match delivery, construction, grid connection, finance and operation so that each party can meet its obligations when payment falls due. If the partners settle a dispute during proceedings, specify payment dates, security and how the settlement can be enforced.
Supply contracts for components and equipment
The supply schedule may cover wind turbines, photovoltaic modules, inverters and storage, or boilers, turbines and generators for conventional plants. Include cables, transformers and controls. Set quality, performance and technical specifications, including applicable editions and test evidence for standards such as IEC 61215 and IEC 61730 for photovoltaic modules.
Set firm dates and remedies for delay. Define the effect of force majeure and notice requirements. Distinguish product warranties, guaranteed module efficiency or turbine output, and remedies for defects or missed performance. Specify inspections, acceptance tests and when a serious defect permits termination.
Check compatibility between packages and allocate transport damage, especially for offshore components. For international orders specify the applicable Incoterms rule, edition and named place or port. FOB and CIF are maritime terms. Check whether the UN Sales Convention (CISG) applies to the sale.
Construction, installation and acceptance
An engineering, procurement and construction (EPC) contractor coordinates design, supply and construction and may deliver a turnkey plant. This reduces the owner’s interface work. Specialised packages can cover offshore monopile foundations, transmission lines and transformers alongside a general contract. Identify who must have completed each predecessor activity before the next contractor starts.
Choose a lump sum or time-and-materials price. Specify milestones and enforceable delay remedies, distinguishing a contractual penalty from an agreed measure of loss. For handover, set test conditions, such as turbine performance measurements, and record completion, defects and reservations in the acceptance report.
Examine defect claims and exclusions of consequential loss. Section 634a BGB provides a five-year limitation period for specified claims concerning structures and related design or supervision. Classify the particular works. Coordinate health and safety requirements, including the applicable rules on the use of work equipment, across contractors.
Grid connection, costs and congestion
The connection agreement defines the technical and legal interface with the distribution or transmission network. Section 17 EnWG governs general connection conditions and section 19 technical requirements. For eligible renewable installations, section 8 EEG governs priority connection and section 9 sets technical requirements according to plant category. Identify the available capacity and the dates by which the connection must be ready.
Specify voltage, frequency, reactive power control, protection systems and grid stability requirements. Separate the necessary connection costs under section 16 EEG from network expansion costs where the EEG applies. For offshore cable works, identify the specific connection regime and delivery responsibilities. Allocate the consequences of congestion or late connection, and examine any proposed delay penalty against the governing rules. Distinguish dispatch instructions and compensation under sections 13a and 14 EnWG as applicable from contractual performance guarantees.
Operation and maintenance
After handover, the O&M agreement assigns operation, inspections, preventive maintenance, repairs and spare parts. Define minimum availability, for example 98% for a wind turbine, together with the measurement period, exclusions and response times. Pay a fixed fee or relate remuneration to output. Allocate downtime and damage, identify warranty interfaces and require access to spares and rapid repair services.
Insurance, disputes and sustainability
Allocate liability for delay, defects and environmental damage. Match construction all-risks and operating liability insurance to those obligations. Choose workable arbitration or mediation provisions across the contracts. Specify supply-chain sustainability obligations and what evidence is required for the project’s environmental, social and governance commitments. Together these provisions connect technical delivery with financing, legal compliance and operation.
Four practical examples
A loan is released only after grid connection. Align the construction milestones with the conditions for drawdown.
The site lease expires before the PPA. Negotiate a renewal option.
Maintenance covers only part of the warranty period. Close the gap in coverage.
A project partner leaves. Secure step-in rights and access to the design documents.