Agreeing additional connection capacity
Negotiate the connection date, any construction contribution and responsibility for reinforcement.
Related guide Electricity and energy tax relief
This worked agreement covers the connection of a German wind or solar generator to the distribution grid. The names and the 5 MW figure are illustrative. Section 8 EEG establishes the connection duty for eligible generators. Under section 7 EEG the operator cannot make performance of its statutory duties conditional on signing a contract.
Model grid connection agreement
1. Preamble
The following parties enter into this model agreement.
- Network operator
XYZ Netz AG, Musterstraße 1, 12345 Musterstadt
Represented by Max Mustermann, acting as an authorised representative. - Connecting customer
ABC Energie GmbH, Energieparkstraße 10, 54321 Energiehausen
Represented by its managing director, Lisa Beispiel.
Purpose
The agreement sets out how the customer’s generator will be connected to the operator’s distribution network and how the connection will operate. Identify the point of connection, applicable legislation and version of the technical connection conditions in the annexes.
2. Scope of work
- The network operator will establish the connection and enable the generator to export electricity at the agreed point.
- The customer will meet the legal and technical requirements for connection and operation of the generating plant.
3. Technical requirements
- Connection conditions:
- The technical connection conditions applicable to the selected voltage level form part of the specification.
- Specify the following parameters in the technical annex.
- Nominal voltage at the connection point and grid frequency (50 Hz). Select the voltage level for this project with the network operator.
- Reactive power capability and compensation.
- Permissible disturbances and evidence of compliance.
- Connection capacity:
- In this example the maximum export capacity is 5 MW at the agreed point of connection.
- Distinguish a contractual export limit under section 8a EEG from statutory redispatch. Specify any agreed limits, time windows, duration, technical controls and the subsequent arrangements.
- Metering:
- Identify the metering point operator responsible for installation and operation under section 3 MsbG. Determine the equipment required for the site.
- Distinguish connection and metering equipment costs under section 16 EEG from metering charges and the allocation under the MsbG.
4. Connection costs
- Allocation of costs:
- For an EEG installation, identify the necessary connection costs borne by the plant operator, including the following items where applicable.
- The connection line from the installation to the point determined under section 8 EEG.
- Document technical inspections and acceptance separately, with the work, payee and basis of the charge identified.
- The network operator bears the statutory network expansion costs.
- Distinguish network optimisation, reinforcement and expansion under section 17 EEG from the plant’s connection line.
- For an EEG installation, identify the necessary connection costs borne by the plant operator, including the following items where applicable.
- Invoicing:
- The operator issues an interim invoice for the agreed connection work and a final, itemised account once work is complete.
5. Responsibilities of the parties
5.1 Network operator
- Complete the connection by the agreed date.
- Maintain the safe operation of the network.
- For interventions affecting a generator, document the statutory basis, instruction, energy volumes and applicable balancing and financial settlement under sections 13a and 14 EnWG.
5.2 Connecting customer
- Construct and operate the plant in accordance with the applicable technical standards, including the relevant VDE application rules.
- Supply the technical documents and test reports.
- Give the operator access to the connection point for maintenance, with notice and safety arrangements agreed in advance.
6. Liability
- Network operator’s liability:
- Start with statutory liability for culpable breaches, including delay in providing the connection where its conditions are met.
- Any restriction relating to consequential loss must address the actual risks and mandatory liability. Review standard terms under section 307 BGB.
- Connecting customer’s liability:
- The customer is liable under the applicable rules for network damage caused by a culpable failure to comply with connection conditions or by improper operation.
- Liability caps:
- A proposed €1 million per-event cap is a negotiation figure. Check the probable loss, insurance, exceptions and enforceability. Liability for intent cannot be waived in advance.
7. Term and termination
- Term:
- The sample agreement takes effect on signature and runs for an indefinite period while the plant remains connected.
- Termination rights:
- The example provides for ordinary termination on twelve months’ notice by either party. Termination of this contract does not extinguish statutory connection rights.
- Address termination for serious breach and agree how permanent decommissioning, disconnection and final billing will be handled.
8. Dispute resolution
- For these commercial parties, agree an operational escalation contact and, if desired, mediation. Sections 111a and 111b EnWG concern consumer complaints to the company and subsequent consumer conciliation.
- For a choice of court at the network operator’s seat, check section 38 ZPO and any exclusive jurisdiction. Otherwise the statutory rules apply.
9. Final provisions
- Specify how amendments are documented and who can sign them. Individually negotiated agreements retain priority over standard terms.
- If a standard term is ineffective, the remaining agreement and the statutory replacement rules are assessed under section 306 BGB.
Alternative clauses
- Cost allocation:
- Option A — Itemise the network operator’s reinforcement works separately from the generator’s necessary connection costs.
- Option B — For a different connection point or optional additional works, document who requested the change, the additional cost and the statutory basis for allocation.
- Export management:
- Option A — Set a fixed export cap under a flexible connection agreement and document how the plant will meet it.
- Option B — Agree different caps for specified time windows. Mandatory system interventions and their statutory settlement remain separate.
- Liability:
- Option A — Negotiate a cap for eligible risks, using €1 million only as an example and preserving mandatory exceptions.
- Option B — Retain statutory liability. Under either approach, liability for intentional conduct cannot be excluded in advance.
Alternative contract structures
- Framework agreement for multiple connections:
- Developers connecting several plants can use one framework agreement.
- Use uniform terms and record each connection point, capacity and commissioning date in a site schedule.
- Simplified connection documentation:
- For a small PV installation, assess the conditions for systems up to 30 kW on a property with an existing connection under section 8 EEG.
- Keep the documents proportionate to the plant while recording its technical and metering requirements.
- Standard connection agreement:
- A standard agreement may suit a community energy project.
- Use clear obligations and a transparent allocation of costs.
Four practical examples
A chemical plant electrifies steam production. Identify when the additional import capacity becomes binding and what happens if reinforcement is delayed.
A battery needs capacity in both directions. State separate import and export capacities in the offer.
The operator requests a construction contribution. Check its legal basis, calculation and the capacity used as the reference.
The connection line crosses a third party’s land. Secure rights for construction, access and future maintenance.
Related advice
Developing power plants and storage
§ 7 EEG · § 8 EEG · § 8a EEG · § 16 EEG · § 17 EEG · § 13a EnWG · § 14 EnWG · § 111a EnWG · § 111b EnWG · § 3 MsbG · § 30 MsbG · § 276 BGB · § 307 BGB · § 38 ZPO