Renewable electricity for on-site use in Germany

A rooftop solar project needs to distinguish four flows: on-site use by the operator, supply to other users, exports and supplementary grid purchases. The legal treatment depends on who operates the equipment, how the lines run and what the contracts provide. This also matters for industrial sites with cogeneration and storage.

1. Operators, grid connection and metering

Calculations based on a 40% EEG surcharge or the former 30 kW and 30 MWh exemption belong to earlier billing periods. Section 61 EEG has been repealed. For current bills, check the purchase and export contracts, network charges and applicable levies. If one company owns the building and another owns the generator, ownership of the land alone does not establish who operates the plant or consumes its electricity.

For an EEG installation, examine section 8 EEG and the technical connection conditions. Section 17 EnWG governs grid connection within its scope. Section 7 EnWG concerns legal unbundling of distribution operators. Where several users share a site, determine whether electricity is supplied to others and whether a regulated distribution network is involved. For shared building supply, section 42b EnWG requires, among other things, quarter-hourly metering and contractual allocation of the building’s electricity.

The metering plan should distinguish generation, immediate use, storage, third-party consumption and grid imports. Sections 29, 30 and 45 MsbG govern the phased smart-meter rollout. More than 7 kW is a relevant threshold for generators within that timetable. Agree responsibilities, installation date, secure transmission, data protection and authorised recipients with the metering operator.

2. EU rules and State aid

Article 21 of Directive (EU) 2018/2001 protects the right to generate, store and consume renewable electricity and sell surplus output, subject to the directive’s conditions. Article 22 addresses renewable energy communities. For a shared project, review membership, allocation of costs, market access and national implementation. Funding also depends on the scheme and, where applicable, EU State aid rules.

3. Electricity tax, VAT and trade tax

Check the particular electricity tax exemption in section 9 StromStG. Capacity, technology, operator and place of withdrawal can all matter. Certain local supplies may also qualify. Identify any required permits, notifications and evidence for the main customs office.

Using a plant’s own solar electricity in its production process is not in itself a withdrawal for non-business purposes. For private use, examine section 3(1b) UStG and any previous input VAT deduction. Section 15 governs deductions on purchases. Section 12(3) sets a zero rate for qualifying PV supplies and installations. Trade tax requires a business within section 2 GewStG. Section 3 no. 32 provides a narrow exemption where the business exclusively generates and markets electricity from a qualifying building-mounted solar plant up to 30 kW.

4. Exports, finance and support

Depending on the model, surplus output can earn a feed-in tariff, a market premium or the price agreed with a buyer. For a 10 kWp rooftop system, use the published rate for its commissioning date and surplus export arrangement. KfW 270 is a promotional loan with its own application terms. Innovative projects seeking EU support, for example through Horizon Europe, need an eligible call and a successful application.

5. Network, registration and evidence

Before commissioning, agree the connection, meter layout and billing arrangements. Register the units and installations under the rules of the Market Master Data Register Ordinance. Record volumes supplied and the responsible counterparties and update them after a change of tenant or owner. Keep historical surcharge records separate from current tax and regulatory documentation.

6. Judgments and regulatory guidance

The Court of Justice’s judgment of 28 March 2019 (C-405/16 P) concerned the financing of Germany’s EEG 2012. The Commission had not established the use of State resources. For local lines serving several customers, the Federal Court of Justice’s order of 13 May 2025 (EnVR 83/20) matters: a German customer installation must fall outside the EU definition of a distribution system. Base the project model on the relevant rates published by the Federal Network Agency and on the actual network and supply arrangements.

Four practical examples

A project company owns the rooftop panels. We examine the lease, day-to-day operation and economic risk to identify the operator.

An independent contractor runs the canteen and uses power from the plant. We meter its consumption separately and identify the supply relationship.

A factory exports surplus power. We coordinate the buyer and settlement for exports with the supplies needed when on-site generation is insufficient.

After a production hall is sold, the plant serves two owners. We review rights over the lines, the new supply contracts and responsibility for metering and billing.

Energy and electricity tax for businesses · Grid connection agreement

§ 61 EEG · § 42b EnWG · § 29 MsbG · § 5 MaStRV · § 9 StromStG · § 12 UStG · § 3 GewStG · Renewable Energy Directive · C-405/16 P · BGH EnVR 83/20 · Published EEG rates · KfW 270